In some places in Gračanica municipality, works on the rehabilitation of the sewerage network have been completed, as was announced from the Department of Urban Planning.
As announced, the rehabilitation of sewage has been completed in Batuse in “Gajeva Street” (310 meters), Ugljare in “Knjaza Miloša Street” (162 m), Kišnica (60 m). The rehabilitation was done in Čaglavica as well, from the Media Center to the brook in the length of 555 meters and from the old road Čaglavica – Ajvalija to the system Ibar-Lepenac, in the length of 680 meters.
The technical acceptance of these works was carried out last week.
The works were carried out on the basis of a long-term project of the rehabilitation and extension of the sewage and water supply network in Gračanica municipality.